24

  No. Execution Period Project Scope of Work Remarks View  
  24 2022.11 ~ 2025.08 TANAJIB IPP 940MW (Cogeneration & Desalination Plant) Electrical & Instrument Works - SAMSUNG C&T Cogeneration & Desalination Plant KSA  
  23 2022.06 ~ 2025.06 Tuwaiq C&F PJT, Main Equipment Installation Work - DHIC Factory KSA  
  22 2019.10 ~ 2024.06 Obra 'C' Thermal Power Station(2 x 660MW) Project - DHIC Power Plant INDIA  
  21 2017.11 ~ 2019.08 Electrical and Instrumentation Work of Fadhili CHP Plant Project - DHIC CHP Plaqnt KSA  
  20 2017.06 ~ 2018.10 The Office and residence of the Embassy of Republic of Korea in Vietnam Project - SAMWHAN CO Electrical Work Vietnam  
  19 2017.05 ~ 2019.05 Installation of POS Technical Rooms for The Line 5 - ALSTOM Transprot SA Metro KSA  
  18 2016.06 ~ 2016.10 CJ FEED INGREDIENT PROJECT VIETNAM FACTORY - Hook up Work - CJ E&C Factory Vietnam  
  17 2016.03 ~ 2016.09 CJ FEED INGREDIENT PROJECT VIETNAM FACTORY - Electrical Work - CJ E&C Factory Vietnam  
  16 2016.03 ~ 2018.03 Upgradation of 220kV Singhigaon substation - BPC / KEPCO Substation Bhutan  
  15 2015.10 ~ 2018.02 Yanbu power and desalination Plant Phase3 - SWCC / Samsung ENG Power Plant KSA